How many points can a project potentially achieve for water metering?

Prepare for the LEED BD+C V4 Exam. Study with flashcards and multiple choice questions, each with hints and explanations. Enhance your chances of success!

In the context of the LEED BD+C V4 green building certification, a project can potentially achieve 1 point for water metering by implementing a necessary measure to track water use. This point is awarded in the Water Efficiency category, specifically under the Water Metering credit.

To comply with this credit, projects are encouraged to install permanent water meters for the building's outdoor and indoor water use. This ongoing monitoring is crucial, as it allows for efficient water management and highlights areas for potential reduction in usage. Accurately measuring water consumption contributes significantly to sustainability goals by promoting accountability and encouraging reductions in water waste.

While it may seem logical to consider higher point values in the context of multiple credits or further enhancements, the specific designation for water metering remains fixed at 1 point. This focus reinforces the necessity of metering while ensuring that projects concentrate their efforts effectively within the framework of available credits.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy